Step-by-step construction procedures

How each service is carried out, from material preparation to curing and finishing.

Athangudi Tiles Manufacturing

Step 1: Raw Material Sieving & Oxide Slurry Preparation
Fine river sand is washed free of silt and sun-dried. White cement, marble powder, and natural mineral oxides are wet-ground into creamy, lump-free colour slurries in individual bowls.
Step 2: Glass Plate Cleaning & Brass Stencil Placement
A polished glass plate is wiped clean and lightly lubricated. The outer cast-iron frame and intricate brass pattern stencil are centered firmly on the glass.
Step 3: Hand-Pouring Colour Slurries & Design Creation
Using brass spoons and pouring cups, the master craftsman pours contrasting oxide slurries into each compartment of the brass stencil simultaneously, then lifts the stencil vertically so the colours meld at the edges without bleeding.
Step 4: Dry Mortar Backing & Hand-Trowel Compaction
A dry 1:3 cement-sand absorbent layer is sprinkled immediately over the wet pigment to draw out excess moisture, followed by the structural backing mortar (18–20 mm total thickness), compacted and leveled with a heavy wooden bat and steel trowel.
Step 5: Initial Setting & Water Tank Curing (10–14 Days)
After 24 hours of initial set on racks, tiles are demoulded from the glass plates and fully submerged in clean water curing tanks for 10 to 14 days so the cement matrix achieves maximum hydration crystal density.
Step 6: Shade Drying & Pre-Dispatch Quality Inspection
Tiles are lifted from the water tanks and stacked vertically in shaded, cross-ventilated racks for 5–7 days of slow curing (never harsh direct sun, which causes warping or craze cracks).
Step 7: Pre-Polishing, Traditional Installation & Joint Sealing
Before or after laying over a 1:4 lime-cement mortar bed with 1.5 mm–2 mm tight joints grouted in pigmented white cement/lime putty, tiles are rubbed with paddy husk (thavudu), coconut coir, and treated with double-boiled linseed oil or natural beeswax.

Full Athangudi Tiles Manufacturing page

Red Oxide Flooring

Step 1: Sub-Base Inspection & Damp-Proofing
The underlying RCC slab or compacted ground-floor PCC bed is checked for level, structural soundness, and rising damp. Ground-floor slabs receive a damp-proof membrane so sub-soil moisture cannot cause efflorescence.
Step 2: Dividing Strip Layout (Paneling)
To prevent random shrinkage cracks over large rooms, 3 mm brass, glass, or heritage Athangudi border strips are set into mortar at 4×4 ft or 5×5 ft grid intervals to exact spirit-level datum.
Step 3: Base Screed Mortar Preparation & Laying (25–30 mm)
After brushing a cement bonding slurry onto the clean slab, a 1:3 cement-coarse river sand leveling bed is laid, compacted with wooden floats, and keyed while green.
Step 4: Dry-Blending Oxide Pigment & Cement (1:3 to 1:4 Ratio)
Natural iron oxide and cement for the entire room are dry-sieved together 4 to 5 times through a fine 100-mesh cloth screen so the colour is 100% uniform across every bay.
Step 5: Oxide Slurry & Top-Coat Application (3–5 mm)
While the base screed is still damp ('green-on-green' monolithic bonding), the oxide-cement paste is applied evenly across the panel and leveled with a straightedge.
Step 6: Timed Steel-Float & River-Stone Burnishing (6–8 Hours)
As the surface loses its water sheen over 4 to 8 hours, masons work on knee-boards in synchronized rounds using progressively smoother steel trowels and rounded river stones to compress the surface capillaries into a glass-smooth skin.
Step 7: Wet Ponding / Sack Curing (14 Days)
Starting the next morning, the floor is kept continuously wet under clean water ponding or wet gunny sacks (avoiding overlapping folds that leave marks) for 10 to 14 days.
Step 8: Fine Wet-Honing & Natural Wax Polishing
Once fully cured and dry (after 15–21 days), the floor is lightly honed with 600–1500 grit diamond water pads if ultra-high gloss is desired, then buffed with natural beeswax and soft cotton flannel.

Full Red Oxide Flooring page

Mud Plastering Work

Step 1: Sub-Soil Selection, Sedimentation & Shrinkage Box Testing
Site or quarry sub-soil is tested using the jar sedimentation test and linear shrinkage box test. Clay-to-sand ratios (typically 1 part clay-rich soil to 2.5–3 parts sharp sand) are calibrated so drying test patties show zero cracking.
Step 2: Dry Sieving, Fibre Mixing & 7-Day Wet Fermentation (Tempering)
Soil and sand are sieved, mixed with 10–15 mm chopped straw, and soaked in water with fermented Kadukkai-jaggery extract for 5 to 7 days. Fermentation breaks down clay platelets and releases natural polysaccharides that dramatically increase water resistance and workability.
Step 3: Wall Surface Preparation & Keying
Brick, adobe, CSEB, or stone walls are brushed free of dust, raked at the mortar joints to 10 mm depth for mechanical key, and thoroughly misted with water until damp but not dripping.
Step 4: Mud Slurry Dash Coat (Bonding Key)
A thin clay-sand-lime/cow-dung bonding slurry is dashed forcefully onto the damp wall and left rough to grip the first coat.
Step 5: First-Coat Application (12–15 mm Leveling Body Coat)
Coarse fiber-reinforced mud mortar is applied by hand and wooden darby rule to true up the wall plane, then cross-scratched ('keyed') as it firms up.
Step 6: Second-Coat Application (5–6 mm Fine Finish Coat)
Once the base coat has dried and completed its shrinkage cycle, the wall is misted and the fine-sieved clay-sand-hemp/typha finish coat is floated smoothly with wooden and sponge floats.
Step 7: Final Texturing & Breathable Sealing
Depending on architectural design, the surface is sponge-textured, steel-burnished, or brushed with a breathable casein/lime wash or linseed-beeswax emulsion in high-touch dado zones.

Full Mud Plastering Work page

Rammed Earth Construction

Step 1: Geotechnical Soil Selection & Sieve/Drop-Ball Testing
Candidate soils are tested for clay plasticity, organic content, and gradation. Unconfined compressive strength test cubes are rammed and cured to verify structural capacity (typically 2.5 to 5.0 MPa for stabilized rammed earth).
Step 2: Raised Masonry/Stone Plinth & Damp-Proof Course (DPC)
Every rammed earth wall begins on a granite or rubble masonry foundation plinth raised at least 450 mm (18 inches) above finished exterior grade with a polymeric/bituminous DPC to prevent capillary ground moisture.
Step 3: Precision Formwork Erection & Electrical Conduit Placement
Rigid shuttering panels (300 mm to 450 mm wide) are bolted onto the plinth, plumbed with laser levels, and fitted with triangular chamfer strips and heavy-duty electrical conduits.
Step 4: Soil Blending & Optimum Moisture Drop-Ball Check
Dry-sieved soil, sand, gravel, and stabilizer are mixed thoroughly. Water is misted in until a hand-squeezed ball dropped from 1.2 meters onto a hard surface shatters into 4–5 cohesive fragments.
Step 5: Layer-by-Layer Filling (150 mm Loose Lifts)
The damp earth mix is shovelled into the formwork in uniform 150 mm loose layers. For polychrome walls, natural mineral oxides are varied between lifts.
Step 6: Manual & Pneumatic Compaction (to 95–100 mm Dense Layer)
Crew members systematically ram the edges first and then the center using steel flat-head rammers or pneumatic tampers until the sound changes from a dull thud to a sharp metallic ring.
Step 7: Immediate Demoulding, Wet Curing & Breathable Water-Repellent Sealing
Shuttering can be stripped immediately after completing a lift, brushed lightly to expose aggregate texture, cured under wet hessian cloth for 14–21 days (for SRE), and treated on exterior faces with breathable potassium methyl siliconate or linseed-turpentine sealer.

Full Rammed Earth Construction page

Lime Plastering Work

Step 1: Lime Slaking, Wet Grinding & Herbal Fermentation
Quicklime is slaked in water tanks and aged into fat lime putty, then wet-ground in a mortar mill with sand and fermented jaggery-Kadukkai water for superior plasticity and tensile strength.
Step 2: Substrate Wetting & Spatterdash Key Coat
Masonry walls are thoroughly soaked for 24 hours so dry bricks do not suck moisture out of the slow-carbonating lime.
Step 3: Base & Scratch Coats (12–15 mm)
Coarse 1:3 lime-sand-surkhi mortar is laid, consolidated with wooden floats over 24–48 hours to close any shrinkage micro-fissures, and mist-cured for 7–10 days.
Step 4: Fine Finish / Burnished Punam Coat (3–5 mm)
Fine lime putty and marble dust are applied in thin layers, compressed with steel trowels and smooth agate/river stones, and treated with coconut water or soapstone polish.

Full Lime Plastering Work page

Cladding Work

Step 1: Material Sorting, Hand-Dressing & Pre-Soaking
Stones are sorted by thickness and natural vein shade, hand-dressed on edges with chisels, and washed free of quarry dust.
Step 2: Substrate Hacking, Key Coat & Mechanical Anchoring
Concrete or brick backing walls are hacked cleanly; heavy stone units above lintel level are secured with SS-304 mechanical pins in addition to mortar.
Step 3: Coursed Laying & Plumb Alignment
Cladding is laid from bottom plinth upward using spacers for uniform 6 mm–10 mm joints, avoiding continuous vertical joints.
Step 4: Recessed Lime-Mortar Pointing & Breathable Sealing
Joints are raked and pointed with weather-struck lime-cement mortar, acid-free washed, and sealed with a matte breathable stone sealer.

Full Cladding Work page

Filler Slab Work

Step 1: Structural Span Design & Centering/Shuttering
Level steel or plywood centering is erected and Chalk-snapped with the exact two-way rib grid, leaving solid concrete zones around column heads, beams, and ceiling fan hooks.
Step 2: Two-Way TMT Rebar Grid Placement & Cover Blocks
Main and distribution steel bars are tied along the rib lines on 20 mm cement cover blocks, with top distribution mesh over the filler units.
Step 3: 12-Hour Water Pre-Soaking & Placement of Terracotta Fillers
Terracotta pots or Mangalore tiles are soaked thoroughly so they do not absorb hydration water from the fresh concrete, then positioned neatly inside each rebar square.
Step 4: Concrete Pouring, Rib Vibration & 14-Day Pond Curing
Concrete is poured carefully into the structural ribs first and compacted with a needle vibrator, followed by a 40–50 mm continuous compression topping slab, then pond-cured for 14 days and waterproofed on the terrace.

Full Filler Slab Work page

Painting Work

Step 1: Surface Scraping, Dust Removal & Dampness Audit
Old flaking plastic paint or efflorescence is scraped back to bare mineral substrate; structural leaks are resolved before priming.
Step 2: Substrate Misting & Mineral Primer Coat
Unlike plastic paints applied on dry walls, lime and mineral paints require pre-misting the plaster with water so the mineral binder penetrates deep into the pores.
Step 3: Cross-Brushed Multi-Coat Application (2–3 Thin Coats)
Using long-bristle natural fibre brushes in a criss-cross motion, 2 to 3 thin coats are applied with 24-hour carbonation intervals (lime wash looks translucent when wet and dries opaque and luminous).
Step 4: Alum / Linseed Fixative Finishing
Exterior and dado coats are fixed with natural alum or linseed oil emulsion to prevent chalking upon touch.

Full Painting Work page